milestone change in CJ20N is not updated in sales order billing plan

Hello guys,

I Update the actual or scheduled date in milestone master data and I expect that sales order billing plan line item  gets updated automatically with the changed date. Why this is not happening?

billing plan is created from WBS milestones.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 12, 2014 at 05:21 AM

    Hi Laimonas,

    check below settings:

    SPRO>sales and distribution> sales> sales document> sales document item> define item category

    maintain billing relevance as I (order related billing) and billing plan type =milestone billing

    now when you maintain milestone billling actual date so this will definitely update actual date in billing plan of sales order line item and remove billing block.

    thanks

    Sunil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      yes these are there.

      I agree that they are tranferred correctly.

      My problem is that change in milestone date is not updated in SO billing plan once it is transferred.

      Looking forward for your support guys.