Hi,

We will be doing two upgraded back to back on all BO Environments.

1- BI 4.2 SP03 Patch 02 Update. (Current - BI 4.1 SP05 Patch 07)
2- Lumira 1.31 update. (Current - Lumira 1.29)

Due to some other urgency we upgraded our pre-production environment (QA, same configuration as PROD) to 4.2 before Lumira 1.31. Now no Lumira reports are accessible in new upgraded BO. (As Lumira is still in 1.29, know fact)

Now we are checking the feasibility to upgraded Development and Production with Lumira first then BI.(To avoid longer downtime for Lumira)

Just wanted to have experts suggestions, what would be the possible risks we may encounter/expect in future/present.

QA - First BI then Lumira upgrade

DEV/PROD - 1st Lumira then BI upgraded.

Thank you.
Subhayan Ghosh.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Denis Konovalov
Feb 01, 2017 at 05:59 PM
0

you should never upgrade Lumira first, always BI, then Lumira as BI upgrade will overwrite Lumira files, webapps etc...

This is why your QA might not be working - you should either upgrade Lumira there or run repair on it...