Skip to Content

Very Huge DB Migration Questions

Hi All,

We'll make a migration for a 7 TB database from AIX-Oracle to Windows-Oracle. System version is ECC 6.00 with NW 7.00

Can you please give your recommendation for minimum process time? Parallel Export-Import, Migmon etc...

Thanks A lot for the answers

Tutku

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 10, 2014 at 02:59 PM

    it always depends.

    have you seen this sap note in case you cannot afford downtime :  1508271 - Oracle Lifecycle Migration Service (formerly O2O/Triple-O)

    regards

    Abdel

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 10, 2014 at 03:32 PM

    What is your Oracle version? Try to check Cross-Platform Transportable Tablespaces option.

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 11, 2014 at 07:05 AM

    Hi,

    I meant Downtime minimisation.

    Regards

    Tutku

    Add comment
    10|10000 characters needed characters exceeded