Longest activity or relation ship duration as critical path

Hi SAP PS Experts,

My client requirement is to get activity as critical path which is longest in project.

Suppose

Scenario 1

A->B->C->D->E

ABCDE are activity with relation shown but it ends on 1 feb 2015 start on 1 jan 2015

Other scenario is

F->G->H Which ends on 15 feb 2015 and starts on 1 jan 2015

So critical path should come scenario 1.

Thanks

Suraj prakash

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Sep 11, 2014 at 10:00 AM

    hi

    I suppose it should work as you wrote. Scenario 1 is longer so it should show a critical path. Are activities ABCDE connected with activities FGH?

    Regards

    Adam

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 11, 2014 at 01:28 PM

    If I understand correctly, the activities are on critical path when their float is zero. It has nothing to do with the longest or shortest activity. So when, any change in the activity dates is going to lead into new dates those activities are said to be in critical path.

    So, I am not sure what you really needed here. Even the report which will show which network is taking longest duration can serve the purpose for you.

    Regards,

    Mahendra

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 11, 2014 at 04:58 PM

    Hi Suraj,

    The critical path is clearly shown in the network graphic overview (In Red Color) [This will also include the activities present in the critical path]. You can also print a copy of this. I hope this is sufficient instead of using a report to verify the critical path.

    Regards

    Varun Rudrabhatla