Planned Delivery Time and Transportation duration- Tlane and Means of Transportation

Dear Experts ,

I have question regarding lead time calculation my SNP

I have

Start Location : A

Destination location: B

I maintained Planned delivery time in ECC- material master as 10 days and cifed to Tlane Product procurement as 10 days

and leave empty in the transportation duration empty so the total lead time is 10 days from start location A to destination location B

now

I maintain 24 hours in Means of transport as transportation duration by truck

now the lead time is 11 days from start location A to destination location B

Now

i leave empty planned delivery time empty and maintain Means of transport duration as 48 hours

so the lead time is 2 days from A to B

does my understanding is correct or not advise please

Regards

Raj

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 10, 2014 at 12:36 PM

    Hi Raj,

    Your understanding is correct.

    I use to setup the transit time in the mean of transport at the transportation lane and keep empty the planned delivery time in MM02, otherwise it is added.

    So you have these two options:

    1- Setup the time at the t-lane and keep emtpy the delivery time.

    2- Setup the time in the planned delivery time and keep empty the time in the t-lane.

    Kind Regards,

    Mariano