on 09-09-2014 3:59 PM
hi all,
Is it possible to Create planned order for each demand within a day in LTP.
for ex.,
Ms04
Planned order- 19.09.2014 4500
demand 19.09.2014 -- 500
demand 19.09.2014 -- 1500
demand 19.09.2014 -- 2500
Its creating like above is it possible to create planned order as follows
We required as follows
Planned order- 19.09.2014 500
Planned order- 19.09.2014 1500
Planned order- 19.09.2014 2500
demand 19.09.2014 -- 500
demand 19.09.2014 -- 1500
demand 19.09.2014 -- 2500
Which setting controls it. we are using individual/collective requirement as 1 for these materials
How the on different dates separate planned orders are generated. please include your valuable inputs
Regards
Muthu Kumar
One information i can add.
My demand is from different material to the same child.
MS04 for child
Planned order- 19.09.2014 4500
demand 19.09.2014 -- From Material1 500
demand 19.09.2014 -- from Material2 1500
demand 19.09.2014 -- From Material3 2500
Can we differentiate this into separate planned orders
Regards
Muthu Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
as mentioned before.
If you do not have a MTO scenario you need to use BAdI MD_ADD_ELEMENTS to simulate individual requrirements within the same date.
Make sure you check for the right scenario, so the coding is not executed during regular MRP
This coding could be a starting point.
could not test it., but you can give it a try.
data: lf_temp_date type DAT00, ls_MDPS type mdps, lf_planr type PLANR.
if IM_PLSC is not initial.
CH_CHANGED = 'X'.
loop at CH_COPY_MDPSX into ls_MDPS where delkz = 'SM'. "for simulated dependent requirements
if ls_MDPS-dat00 = lf_temp_date.
ls_mdps-planr = lf_planr + 1.
lf_planr = ls_mdps-planr.
else.
lf_planr = ls_mdps-planr.
endif.
lf_temp_date = ls_mdps-dat00.
endloop.
endif.
If you need to have separate planned order depending on header material you can also check for this in addition to requirement date
Uli
Thanks KÖller´.
We face a new challenge when we do this we have pir at assembly level and sub assembly level.
The planned order generated at sub assembly get summed up for both PIR and depedent requirement.
In this case this Plnr number range doesnt works. Because one demand is dependent demand and other is PIR demand but single planned order generated for both.
Regards
Muthu Kumar
If you don't have a MTO scenario for the header material, its not possible to achieve that with sap standard.
MRP will always create one planned order for requiremnts on the same date.
You can use BAdI MD_ADD_ELEMENTS and change planning segment in CH_COPY_MDPSX so its different for the requirements on the same date.
This would be like a individual requirement.
Regards,
Uli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.