Skip to Content
avatar image
Former Member

run BOMBOS en masse

Hi all,

Is it possible to send more than one material into the BOMBOS queue, even if nothing changes in the recipe? we have a need to populate the exact compositions or standard compositions en masse.

thanks!

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 09, 2014 at 03:05 PM

    Hello Scott,

    Yes it is possible to send more than material in BOM BOS Que but if nothing is changed at BOM level no work list is generated.


    If you are using Recipe Development or Recipe Management than BOM-BOS is not required you can transfer the composition to primary out put using the RD(NWBC) function.


    Normally this should populates in ECBP (Exact composition based on Product's) but this can be configured if there is need to populate in standard composition ( Not Preferred)


    Hope this helps.


    Gopi Dadheech

    Add comment
    10|10000 characters needed characters exceeded