No Price could be determined for material/batch in plant xxxx in MB31

Hi,

When doing good receipt through MB31 for discrete mfg. process, we are getting this error "No Price could be determined for material/batch in plant xxxx"

There is assignment of WBS element.

here we have created one production order with CO01 for a Material with Price Control "V" and i am using Ref. Routing with different operations keeping standard values for different activities blank and i am putting values in these fields during the order confirmation with CO11N and assigning BOM components directly to the order.No BOM is created as standard.

So while do the GR for Order With MB31 system is showing error massage that is

No price could be determined for material/batch

May I know the reason for it.

regards

Message was edited by: Pari SS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Sep 09, 2014 at 10:58 AM

    Hi,

    There is no price maintained for the material. Due to this system is throwing error message. Please maintain the price for the material. After that do GR.

    Regards,

    Mukthar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 10, 2014 at 09:08 AM

    Hi,

    What i understood from your process is "Material is split valuation- maintained"

    So can you please check for Material Master in MM03-with Valuation Type-XXX in Accounting tab price is maintained...

    Coz ....in Split valuation Header & Batch/Valuation type (Lower level) price has to maintained.