All default routing value has to be changed, while changed the work center in production order

Dear friends,

our client they want to change the work center in production order.according to production version work center also they are changed.so while change the WC,all the default value has be changed as per routing what we maintained in routing.At present we have to enter the manually change the W.C as well as set up time and operation time enter manually.Any other option to do the automatically capture value from routing while change in Work center in production order.pl help me on this.

Thanks&Regards

Sabhapathy R

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Sep 09, 2014 at 10:36 AM

    Hello,

    You can find the default values, those mat be set when entering a new work center to a routing, in the default values tab of the work center. Standart hours cannot be given default values in a work center. As an alternative method, you can change routings in mass with transaction CEWB. To do this you can load the task operations in CEWB, select the column you want to change and follow Extras->Mass change from the menu.

    Regards.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Özgen Canan

      Hi Ozgen,

      If i changed the CEWB in new value what is the impact ?

      I want to first one should default,second line routing ,whenever i changed the w.c in production order that value has to pick from 2 line routing value.Is that possible  how CEWB help on this.pl do the needful.

      Regards,

      Sabhapathy R

  • avatar image
    Former Member
    Sep 09, 2014 at 10:45 AM

    Hi Sabhapathy,

    For your request, in standard, you may try to use CEWB transaction. CA85 would only help in mass changing work center in the routing and it would fall short on changing the activity times as you require.

    In my experience, we have also created a Custom transaction to Mass Update Routing via Excel (Upload, Download and Create). That custom transaction was pretty useful in updating Work center and activity times en mass.

    BR

    Rahul

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Kiran Madhurakavi

      Hi Kiran,

      If i changed the CEWB in new value what is the impact ?

      I want to first one should default,second line routing ,whenever i changed the w.c in production order that value has to pick from 2 line routing value.Is that possible  how CEWB help on this.pl do the needful.

      Regards,