psa to dso data load issue

Hello Gurus,

We are facing an issue while loading data into a DSO. Recently upgraded our hana level to 82. Before the upgrade we had no issues in loading data to same data target (no change to transformations/dtp) also the data volume is nearly same i.e. 20-30million. I checked load by changing the parallel pro cesses to 1 from 3, result is the same error (error in kernel, SYSTEM_CORE_DUMPED, program CL_RSODSO_UPDATE_DS is terminated). After this error basis upgraded the kernel to newer version.

BW 7.4 SP04, HANA patch 82

Kernel 740, pkg lvl 73

Error in the SAP kernel

The current ABAP program "CL_RSODSO_UPDATE_DS===========CP" had to be

terminated because the ABAP processor detected a system error.

help is appreciated.


Thanks,

Maddy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 30, 2014 at 05:46 PM

    this issue is solved by updating kernel patch.