Heuristic run @ destination location is creating the purchase requisition without source plant

67 Views

Hello All,

Trust you are doing well.

Believe this is the good time to connect with you all get some advice on the below mentioned scenario:

Material (XXXXXX) is discontinued at source location (Plant specific material status: 90) but the same material
(XXXXXX) is still used in destination location (plant specific material status: 60). Here heuristic run @ destination location is creating the purchase requisition without source plant.

Here the customer expectation is that “SNP should not create the order, since the material is discontinued in source plant”

Could you please advise?