on 09-04-2014 8:29 AM
dear All,
i want to get the project status by knowing the last activity fully confirmed in CJ20N.
please suggest me the tables and links to get the last activity in the project which is fully confirmed (100%)
thanks.
Hi,
Try AFRU table, Pass AUFNR as Network and VORNR as activity. Fetch the data. There will be a field called Final Confirmation.If it is X, then it is confirmed.
Not sure, if this is what you are looking for. Else, you can check it through JEST and JCDS table.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks amit...
now am getting the final confirmed activity with dates as per the logic given by you. but i want link Activity and WBS. can you pls help me?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suhas,
You got to use the following tables to get the details.
1. PROJ - For Projects
2, PRPS- For WBS
3. AFVC- For Activities
4. JEST or JCDS- For current status of the activities. .
From the first three tables get the Activities which are maintained in your Project. Then Pass the activity OBJNR to the JEST or JCDS for getting the Fully Confirmed Status..
Hope it helps
Cheers
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.