dear All,

i want to get the project status by knowing the last activity fully confirmed in CJ20N.

please suggest me the tables and links to get the last activity in the project which is fully confirmed (100%)

thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Try AFRU table, Pass AUFNR as Network and VORNR as activity. Fetch the data. There will be a field called Final Confirmation.If it is X, then it is confirmed.

Not sure, if this is what you are looking for. Else, you can check it through JEST and JCDS table.

Regards,

Amit

Answers (2)

Answers (2)

0 Kudos

Thanks amit...

now am getting the final confirmed activity with dates as per the logic given by you. but i want link Activity and WBS. can you pls help me?

sammar81
Employee
Employee
0 Kudos

join the AFVC table with PRPS. You have the field WBS in the AFVC table. So thats your link.. to get the WBS..

0 Kudos

yeah i have that link...

PROJ to PRPS

PRPS to AFVC

in AFRU as u said am getting the activity number which is confirmed 100%

and now when i want to get the last activity which is confirmed 100%, there is no linkage from AFRU to AFVC to reach upto PRPS

sammar81
Employee
Employee
0 Kudos

The link  between AFVC and AFRU is simple.. These fields give you the linkage..

AFVC     AUFPL     AFRU     AUFPL

AFVC     APLZL     AFRU     APLZL

And AUFPL you can get from AFKO table by passing the AUFNR.  which is your network number..

Hope it helps you..

Cheers

Sammar

0 Kudos

thanks man.....it worked. you solved a big head ache

sammar81
Employee
Employee
0 Kudos

no worries.. enjoy..

sammar81
Employee
Employee
0 Kudos

Hi Suhas,

You got to use the following tables to get the details.

1. PROJ - For Projects

2, PRPS- For WBS

3. AFVC- For Activities

4. JEST or JCDS- For current status of the activities. .

From the first three tables get the Activities which are maintained in your Project. Then Pass the activity OBJNR to the JEST or JCDS for getting the Fully Confirmed Status..

Hope it helps

Cheers

Sammar