09-03-2014 10:27 AM
Hi Experts,
I have a requirement to capture the changed budget values in the CJR2 transaction while saving.
Kindly tell me which exit or BADI can be used.
Thanks & regards,
Prashantha T
09-03-2014 10:44 AM
Hi Prashantha,
I don't think if there are any User Exits/Badi's for CJR2.
Thanks
Sri
09-03-2014 10:47 AM
Hi Srilashmi,
Thanks for your reply.
But we have the requirement to get the budget values before posting the same into CJ40 transaction.
Is there any other way out to achieve it?
Thanks & regards,
Prashantha T
09-03-2014 12:27 PM
You could try to code a customer-exit in a CO defined validation (OKC7) or substitution (OKC9) ?
Regards,
Raymond