Hi,

I have an issue with report PT_ERL00 - the report is throwing a customised error for an employee (25.03.2013), however the employee is present on that day. See below screenshots.

Also you can see in CAT2 that the employees times have been recorded and approved. They have then been transferred to the PA30 record.

When I run Time Evaluation (RPTIME00) for the employee there is no issues with this date (25.03.2013).

Any help or guidance on this matter would be greatly appreciated.

PT_ERL00

PA30 - Attendances

CAT2

Thanks,

Brian

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member193652
Active Contributor
0 Kudos

Hi Brian,

Run PT60 again just for this day and consider output log in detail to find the message or go into PT40 and find time management messges for this EE. Here by double click you can go into message detail.

By the way, I see there is just an attendance record for 1 hour. What about the rest of working hours? Does EE have any clock-in/out? Maybe you would create a daily attendance record not hourly.

Regards,

Omid

Former Member
0 Kudos

Hi Omid,

Thanks for the reply - this is the message detail when I go into PT40. How can I find the time management messages?

former_member193652
Active Contributor
0 Kudos

Hi Brian,

It seems EE is absence on 06.03.2014 and there is no any clock-in/out. The absence record that comes from IT2001 may be generated automatically by system.

If you check PT66 you will see this is a working day for EE based on its work schedule rule. So system works well and stop time evaluation by generating error message.

If you would system go ahead you should implement an automatic absence generation. In this way system will generate an absence record and the next day by running time evaluation system won't stop on this day because the day before a record has been generated and already there is in IT2001.

Regards,

Omid

vianshu
Active Contributor
0 Kudos

Hi Brian,

Can you share screenshot of the PCR which is generating this error message?

Thanks and regards,
Vivek Barnwal

Former Member
0 Kudos

Hi Vivek,

Which PCR? As far am I am aware there is no PCR in PT_ERL00?

There are no issues with the date (25.03.2013) when I run the Time Evaluation.

Thanks,

Brian

vianshu
Active Contributor
0 Kudos

This message would have got generated by operation COLER in time evaluation.

Ideally, these messages should be processed after the issue has been rectified.

Thanks and regards,

Vivek Barnwal

Former Member
0 Kudos

Ok, thanks Vivek.

So I need to find which PCR contains the COLER operation in my schema, and then troubleshoot from there?

Thanks,

Brian

vianshu
Active Contributor
0 Kudos

Yes...this message should be coming from there.

Thanks and regards,

Vivek