on 01-24-2017 10:27 AM
Hi all,
i have created in IDT realational connection based on ABAP function. When i create a single source universe everything works fine but when i create multisource universe, date fields from the abap function are not visible.
Any ideas?
Best regards,
Martin Zluky
have you tried the refresh structure in Data Foundation?
According to this sap note restart the BO services and try again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
you were right the whole time. I forgot that we have divided the APS into 5 parts so i forgot to restart the one with connectivity services. Now it works like you said and the note is a good one too.
Big thanks!
Best regards,
Martin Zluky
Hi all,
The problem happens with new fields that we have added to existing abap function. So it doesnt matter if it is a date field, char, or any other type. I tried to create new connection, new shortcut connection but it doesnt work... Still the same issue.
Best regards,
Martin Zluky
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Stop and Start of the Adaptive Processing Server and try.
or if still you have the issue then share the screenshot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
25 | |
12 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.