on 08-26-2014 8:24 AM
Dear All,
We are Operating and Maintenance company for Power Generation and Water desalinisation plants. I am looking for the help to find out the ways to use Controlling module for the managment accounting/costing.
PCA is acive in new GL and running fine.
Following things has to be extracted out of SAP controlling.
1. Material/Service wise quantity & price variance
2. Total cost for each line of production (i.e. Power & Water)
3. Bifurcation of total cost of production in its Components and
underlying drivers of components (i.e.
4. Production cost of per MW of Power or M3 of water, what are the
components of cost.
5. Cost of production of each unit (i.e. per MW cost unit wise e.g.
Unit 10, Unit 20 )
Hi,
Order Selection Report= KOC4 Or S_ALR_87013127 - Order Selection
Plant Qty & Actual Qty
Actual Debit Cost =(Goods Issue + Prod Confirmation Cost)
Actual Fixed Cost= (Production Cost Power+ Labour+ MOH)
Target/Actual Cost Credit= (Goods Receipt)
The Above fields will match with KKBC_ORD (Order Wise Report as Goods Issue+ Prod Cost (Confirmation)+ Goods Receipts)
Note: for more Bifurcation of total cost of production in its Components and
underlying drivers of components (i.e. need to analyze in Order Report-KKBC_ORD or Cost Center Report KSB1 with Material wise. (To arrive mirco level cost of unit for Material Powe/Labour/MOH need to customize report.
Regd,
Khan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.