Can you please help to understand the use for value category from OPI2/OPI8? In CJVC we have all cost elements assigned to cost element group and cost element group assigned to value category. What is this Value category?

Exista any table in SE16 which can export all value categories, cost element groups and cost elements? This is half PS and half CO.

Thank you.

Rodica

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

the value category customizing is essential for PS reporting (see note 676123; following lines

are quotes from this note). :

...

     Heading 1: Value category customizing

     In the project information database the value category plays the role,

     that cost elements, commitment items and statistical key figures have in

     the controlling tables, report-writer reports / report painter reports

     and line item reports.

     The value category customizing controls this re-keying process from the

     controlling tables to the project information database. It is essential!

     This customizing must be set up correctly and completely. Otherwise you

     will get unpredictably wrong values in the hierarchy reports, the

     structure overview, earned value analysis and in the project planning

     board.

....

    Heading 1: * Project Information Database*

     The *project information database *- table RPSCO - is the value table

     (no quantities!) that serves as common database for:

         o  Hierarchy Reports

         o  Structure Overview

         o  Progress Analysis (earned value)

         o  Project Planning Board.

     It contains values from controlling (costs, revenues, commitment) and

     PS cash management (expenses, receipts, cash commitment, planned

     payments ...).

     For earned value analysis table RPSQT contains the necessary quantities.

     The values in this table occur from statistical keyfigure records in

     controlling.

     That way you can design hierarchy reports that are able to report on all

     these values in one single report.

...

The value categoy customizing is done using transaction CJVC. As stated in note 676123

....

     1.  Please use transaction CJVC to check your value category

         customizing.

     All red AND yellow lights shown there have to be eliminated

     by correcting and completing your value category customizing. In order

     to do that, please review your customizing following these guidelines:

         a) Each cost element/commitment item/stat. key figure HAS TO BE

            ASSIGNED exactly once to a value category. Assigning them to more

            or less than one value category will lead to unpredictable

            results.

         b) This is nessessary EVEN, IF YOU NEVER WANT TO SEE those values.

            In that case you can block the update to table RPSCO. To block

            the update please create an assignment line to a value category

            and activate the 'suppress' indicator on the assignment detail

            screen.

         c) Only

            - Cost elements of the same cost element type

            - Commitment items of the same item category and

            - Statistical key figures of the same unit of measure and the

            same key figure category

            are allowed to be assigned to the same value category. Other

            and/or mixed assignments will lead to unpredictable results like

            mixing costs and revenues in columns or rows!

         d) When you create the value categories, that replace the cost

            element/commitment item/statistical key figure in the project

            information database, check for the correct setting of the radio

            button:

            COSTS: for value categories meant to be used for cost elements of

            type 1 ('costs'); for value categories meant to be used for

            commitment items for expenses

            REVENUES: for value categories meant to be used for cost elements

            of type 11 or 12 ('revenues'); for value categories meant to be

            used for commitment items for receipts.

            If you want to assign STATISTICAL KEY FIGURES to the value

            category, you indicate, whether the value category should contain

            key figures with totals values characteristic or fixed values

            characteristic.

            These settings are valid for all cost elements/commitment

            items/statistical key figures you assign to the value category.

     2.  If all red and yellow lights in transaction CJVC are eliminated,

         please rebuild the Project Information Database (table RPSCO) by

         transaction CJEN. Without this, changes carried out in your value

         category customizing won't have any effect. That is necessary after

         all changes in value category customizing, that affect values

         already posted. Running CJEN is not dangerous.

     3.  Please rebuild the assigned values using transaction CJBN

         afterwards, if you use budgeting.

     4.  Performance tip:

         You can create more than one assignement line for one value

         category. This is possible, because the assignment lines do not only

         contain the controlling area and the value category but also a

         counter (1-999).

         If you assign cost elements or cost element intervals to the value

         category instead of cost element groups, you save the time, that

         otherwise would be consumed for the explosion of the cost element

         group.

         For being able to do that easily, please consider the following:

         Please use allways the same number of digits for all cost elements

         and revenue elements - to have a reserve eventually 1 or two digits

         more than you initially need. The field for cost element is an

         alphanumeric field and is lexically sorted. If you do not do it that

         way, you will have problems defining intervals. So please use the

         same number of digits for all cost elements. The same is for

         commitment items and statistical key figures.

     This setup should be checked regularly to make sure, that all values are

     updated to the project information database in the correct way! There

     should be a special focus on newly created cost elements / commitment

     items / statistical key figures.

Regards

Varun

Former Member
0 Kudos

Thank you!

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Rodica,

Check below table

TPIK3 - Assignment Table: Cost Elements -> Value Categories

RPSCO - Project info database: Costs, revenues, finances

Regards

Tushar


Former Member
0 Kudos

Hi Rodica,

Go through this note,

676123 - Project Information Database / Value Category Customizing


I believe it has all the required information you need.

Regards,

Gokul

Former Member
0 Kudos

Gokul.

Where I can read SAP notes?

Unfortunately until Monday I cannot check anything in the system.

Thanks again.

Rodica

Former Member
0 Kudos

Go to this site service.sap.com/notes and put in the note number.

I could not find your mail id in your profile. Else i could have mailed it to you.

Former Member
0 Kudos

I do not have access to the service.sap.com/notes