How do I link manufacturing label designed in wwi to print automatically during the time of goods receipts from the production

Hello

Is there any way to link label to print automatically from the printer at the time of TECO ,Goods receipts from production and PGI at the time of delivery to the customers .

Regards,

M D

Add comment
10|10000 characters needed characters exceeded

3 Answers

  • Best Answer
    Posted on Aug 13, 2014 at 06:18 PM
    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 18, 2014 at 09:25 AM

    Hi !

    GLM supports Automatic Label Print requests & Automatic Label Printing(immediately after generation of automatic print requests). But this is limited to Delivery order, Process Order & Handling Unit as standard. For other scenarios, you will have to customize.

    Automatic Print Request Generation - Global Label Management (EHS-SAF-GLM) - SAP Library

    http://help.sap.com/erp2005_ehp_07/helpdata/en/32/a81051e71e2514e10000000a44176d/content.htm?frameset=/en/00/704e3340074776bb6877aa7edb7394/frameset.htm&current_toc=/en/54/c86cb93bdc4d698eb8e2524b59692b/plain.htm&node_id=38


    But this is possible with "Enhanced" GLM. It's better explained here,


    Regards

    Subash Sankar


    Add comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 18, 2014 at 01:51 PM

    hello Subash,

    Looks like this is giving solution only for ehp7 we are on ehp5 right now . Do we have a solution for ehp5 like using any user  exit(PPCO0001 ) as I have found one which tells us to implement some customer exit for this scenario .

    Regards,

    M D

    Add comment
    10|10000 characters needed characters exceeded

    • Dear M D

      for that e.g. check:

      But first you need to understand the use of "userexits". In most cases they have been designed to be used in "specific" scenario. But clealry a userexit is a "custoimer specifci implmentation" there fore you can do what you would like to do. So in theory you can use this exit /enhance it may be) and "trigger" if needed GLM printing; but this is not SAP process as SAP is belivieng that you will use GHLM different

      IN any case. check exits like you have mentioned. Check the paramater availbel in the exit. Check if you are able to "collect" the data required for GLm etc.

      C.B.