on 08-12-2014 8:10 PM
If more than one work center used for single internal activity how can work center be allocated ?
Hi Yogesh,
I understand that, you have a project activity in which different groups of people are working and you want to plan costs for all these groups of employees under the same project activity.
To achieve this, create different activity elements under that activity and assign specific WCs and Work duration to all these activity elements so that system will calculate aggregated costs and scheduling dates accordingly.
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try to use activity elements with different work centers for that activity
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please provide us your requirement to understand the process to define in the system
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Search the forum.
This topic has already been discussed a lot of times in the forum.
Besides, next time onwards whenever you post a query please make sure you explain the context. Its difficult for forum members to respond unless they understand your query completely.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.