PO number in shipment cost document

Hi All

we have cancelled the service entry sheet for one line item in VI02 , i normal scenerio the entry sheet number and PO number will disappear for the shipment cosr document . but here only entry sheet number got disappeared , and PO number is still there . SO because of this we are unable to do the settlement again for this line item .

Could you please suggest us how should can we delete the PO number from the shipment cost document , and what went wrong in our process because of this only entry sheet got disappeared and PO number is existing even when we had cancelled the service entry sheet.

Thanks in Advance


Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 10, 2014 at 03:03 PM

    Hello,

    Go to SCD and check if Cancel option available in Settlement tab.

    SCD (VI02) --> Item details --> Settlement tab --> Select cancel check box and Save

    Cheers,

    Nag