on 08-05-2014 2:36 PM
Dear experts,
after run MD02, system creates ONE grouped planned order for every necessities of same day.
We need generate individual planned orders (EACH planned order for EACH need),
Is it possible? How to do it?
Please see Q&A 6 in OSS note 550568 - FAQ: MRP run (MD01, MD02, MD03, MDBT,...)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Jürgen, tks a lot!
Note 550568 shows me:
6. Question: There are several requirements on one day. Is it possible that the MRP creates a separate procurement proposal for every requirement?
Answer: Same as for the daily lot size with a number of periods = 1 (lot size TB), requirements of one day are also grouped into one procurement proposal for the lot-for-lot order quantity (lot size EX) (see documentation for the lot-for-lot order quantity). Separate procurement proposals can be achieved only if you work with make-to-order production. Here, the requirements are managed in separate planning segments of the stock/requirements list.
Then, answer is NOT! It's not possible separate individual daily proposal for purchasing to unrestricted stock.