on 08-04-2014 11:38 AM
Hello All,
I have added a material in BOM with Item cat 'N' (Non-stock). I want to bring the functionality of sub-contracting process
(Assembly raw material with price from Material master and the sub-contracting cost from PIR).
I am not getting any amount in the 'Itemization' view for Sub-contracting'.
Anything I am missing related to BOM Item category? Also, i want to know how can i bring the component for 'Sub-contracting' in the Itemization view of costing.
Thanks in advance!
BR, D'nesh
Have you updated the G/L account in Cost component structure OKTZ? Just a try.