Maximum Loop Count - Operation Maintenance

Hi,

We want to set the Maximum Loop Count in the operation maintenance, but we realize this has no control how many times SFC can be started at this operation, are we missing any configurations to trigger this functionality?

We tried if we configure the Maximum Loop Count in the Router Maintenance, it works properly. But we are looking for a behaviour that works on the Operation level only, not the operation in the router.

Please advice whether I need configure anything else to trigger this functionality.

Thanks and Regards,

Leon

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 04, 2014 at 05:47 AM

    Hi Leon,

    This option should work the same way for both Operation Maintenance and Routing Maintenance. Maybe there is a bug in your release because last time I tested it in ME 6.1 it worked fine. And I do not see any relevant fix.

    Regards,

    Sergiy

    Add comment
    10|10000 characters needed characters exceeded

    • Leon Lu Konstantin Chernega

      Hi Konstantin, Sergiy,

      You are right, the behavour how to use the Maximum Loop Count in Operation Maint is what like you said, it shoudl not be a bug, though this is not what I am expecting. I will recall the ticket as well.

      Thanks for the clarification.

      Best regards,

      Leon