Hi gurus,

I have a PIR for 10000 PC, for example. i have min and max lot size defined in MRP1 as 4800 and 5200. I want MRP to create two planned orders with quantity in between 4800 and 5200. what should i do for it?

thank you in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

If you have a max lot size of 5200 MRP should be already generating an order of 5200 and if the min lot size is 4800, another order of this quantity should be genreated.Did you already run MRP for this material? What is the results?

Regards,

Caetano