Publication schedule fails

Hi,

I am facing a issue while scheduling publications in BO XI3.1 SP6 FP6.2,

Publication uses webi reports.

Error Message: [0 recipients processed]

Any suggestions would be helpful.

Thanks,

Manoj

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Jul 25, 2014 at 10:34 AM

    could you check your Publication's Dynamic Recipients tab

    and follow the steps with below document

    Report Bursting Technique in BO XI 3.1

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 25, 2014 at 10:41 AM

    Hi Manoj,

    There can be many reasons ,

    1.User/Report/folder may not have the access rights to deliver the output to end users.

    You may need to assign add objects access right.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Pandey and Sathish,

      Thank you for immediate reply.

      I could tried the steps from SAP note: 1726111

      Cleared the webi processing server cache and restarted the services. Publication works fine.

      However issue replicates back after 3 or 4 days.

      Please suggest if we need to configure any metrics at server level or is there any other reasons on replication of issue again and again.

      Thanks,

      Manoj.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.