We have some fairly high volume suppliers on SNC, and when they have 60 PO Confirmations to create an ASN for, the system is timing out before all PO Confirmation lines can be selected. I have 2 questions:

1) is there a way to create an ASN, save it as draft and later add additional PO COnfirmation lines to it by selecting from the due list?

2) how can we adjust the timeout settings in SNC so we have an hour with no activity or even 30 minutes? Right now, we time out in under 5 minutes.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jul 25, 2014 at 08:50 AM

    Hi Michele,

    You can use file upload and download functionality.

    File for Due List for Purchasing Documents - File Transfer - SAP Library

    Regards,

    Nikhil