on 07-24-2014 10:22 PM
Hi All...
we have a requirment to change start time which is system genrated for specific orders in product view while saving.
Initially thought of using BADI'/SAPAPO/SMOY_PUB_APP' but by this time time is populated and is coming as a import parameter thus not allowing to change.
if we are not able to change in APO is it possible to change in ECC while order is getting created?
Does any BADI/Exit that solves this requirement?
Thanks
Dev
Hi
Found solution , In APO we don't have any exists/BADI which allows to override creation time in APO and was able to make change in ECC for incoming que (in ECC).
Below are enhancements that SAP is provided for purchase orders that are coming from APO.
Enhancement:'CIFPUR02' and in this function module 'EXIT_SAPLMEPI_003' solved this issue.
Thanks Rajiv for your inputs.
Thanks,
Dev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dev,
Can you specify which object start dates would you like to change in RRP3?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dav,
The receipt time is decide based on period factor you enter for the material master. If eneter as 0 then it is begining of the period and 0.5 in the middle and 1 is at the end of the period.
if period factor eneter as 0 it will show time as 00:00
0.5 will show as 12;00
and 1 will show as 23:59:59