CJ88 and "with order" flag

Former Member
0 Kudos

Hi guru,

if I run CJ88 and set flag "with orders", the system doesn't settle cost from production order / networks to WBS element

Please, could you tell me where I can check in order to fix this problem?

Thanks

Regards

Raffaele

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Raffaele,

In co03 assignment tab you must find WBS if you are carrying out production against a project.

Please let me know if my understanding is correct or not.

Regards

Varun

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Raffaele,

You will need to create a settlement profile for this and check assignment to order type(using kot2).

Please find this out with your PP consultant before configuring the same. Please refer the following link for more information.

Settlement Rule - Production Orders (PP-SFC) - SAP Library

Regards

Varun

Former Member
0 Kudos

Hi Raffaele,

Its only when the production order is finally confirmed (which will happen after the production is completed) the system posts the goods receipt to the project stock. Are you able to see the project stock getting updated after the production order is confirmed? I think the actual costs shall only come into PS reports if the production order is confirmed.

The system automatically assigns a settlement rule to the production order when the order is created. Try using a network as the settlement receiver for the production order and carry out periodic (or) full settlement .

Regards

Varun

Former Member
0 Kudos

Hi varun,

my problem is the system doesn't assign automatically the wbs element to settlement rule in production order. This means that, probably, there is something wrong in configuration

Could you help me to understand where the configuration is wrong?

Thanks

Regards

Raffaele

Former Member
0 Kudos

Hi Raffaele,

As I understand, you are linking the FG to network activity. when you recieve FG in stock after production order processing, you can issue the same to network.The cost incurred in production order will be shown under account assigned WBS. Are you issuing the goods to the network after the production order is getting processed?

Regards

Varun

Former Member
0 Kudos

Hi varun,

I'm not issuing the goods because at the end of month, the production is not completed yet

is this a problem?

Thanks

regards

Former Member
0 Kudos

Hi Raffaele,

Can you tell me the error that you have been observing while trying to settle the costs from order/networks to WBS element?

If there are no costs present at the activity level the system will not be in a position to settle them to WBSe. Kindly check cji3 report for that network and activity. Also please ensure that the period and fiscal year that you have been entering at the time of settlement is correct.

Regards

Varun

Former Member
0 Kudos

Hi Varun,

thanks for your reply. At the activity level, I don't have any cost but I have it at production order level. I work with project stock.

Now, in order to run result analysis, I need to have costs at billing element level, so my idea is to settle first costs from ntw/production order to WBS element and then run RA

Could you help me?

Thanks

Regards

Raffaele