DN Order scheduling for STO and SO works differently

Hi experts,

I have a question on the order scheduling for DN, I have 2 cases for DN for STO and DN for SO where I am seeing GATP happened differently in both cases.


Case 1: When DN for STO, it will perform GATP again thus give a new Good Issue date. So the GI date sometimes may differ GI date from STO (depends on factory shipping calendar).

Case 2: If DN for SO, the system always use GI date from SO directly. So GI date will always same in DN and SO.

May I know what setting may affect the behavior above? Is this standard GATP scheduling?

Thanks.

HH

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 25, 2014 at 08:07 PM

    what do you mean by DN  ? is it delivery ?

    Scheduling will behave as you configure it ? Ideally you would want SO & STO to have similar sceduling criteria , if there is no special requirement to make it different.

    Regards,

    Jit

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 31, 2014 at 11:39 AM

    Hello HH Ooi,


    There are significant amount of differences in the way things have been designed in ATP functionality for SO and STO. So, you don't need to get surprised of the issues in STO scheduling. As part of the implementation, to make the STO scheduling work, you need to do many enhancements and many OSS note implementation will also take place.

    Babu Kilari