Reg. Auto assignment of product version while run MRP

Hello All,

Need your help.
while running MRP, system is automatically assigning first PV to planned order.

but I want user to select PV while converting planned order to process order.

please help me where to check this configuration.

Thanks,

Archana

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Jul 19, 2014 at 09:49 AM

    Hi,

    Check in configuration in COR4 for the combination of Plant and Order type select Manual Production version as shown below....

    Thanks

    Kumar


    pastedImage_0.png (30.6 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 19, 2014 at 11:09 AM

    Hello Pillai,,

    Please refer this thread for your issue,

    If you don't want to use first PV then block this production version and create new one,
    And PV also depend on the Lot size selection.

    Remove selection method "blank"

    I hope this information helpful to you

    Regards

    Umesh Mali

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.