Update quantity in planned receipt in RO

How to update the Planned receipt quantity in Replenshinment order. Is there any BADI for this.

We have some cutom logic to calculate the quantity and we need to change this Planned receipt quantity with this new value.

test1.jpeg (100.9 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2014 at 07:39 AM

    Hi Lekha,

    What is the scenario you have ?

    Supplier can manually update planned receipt in SNC WebUI or using SMI planned receipt file download/upload functionality.

    If it is EDI supplier then you can ProductActivityNotification_In towards SNC from PI.

    Regards,

    Nikhil

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.