on 07-14-2014 8:27 PM
Uma Pathy,
For 1 st level Raw paint - SFG what is lot size you are using in material master MRP1 view try with EX lot for lot order quantity and Rerun MRP and see if that works.
Br
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mr.KK,
I am always maintain the material master lot size is EX only, i got the point what is the lot size control having the same MRP 1 view Max.lot size this is split up the batch qty based on this setting.
thanks
& one more clarification i need i have create some new material for both SFG , FG.
I have run the MRP that time FG only created the planned order other wise 2 nd level and 1 st level SFG not created the planned order.
I have checked and maintain Mrp type : PD, Lot size: EX, Ind / coll indicator : 2 , MRP controller, BOM status all are is correct but Planned order not created ?
Kindly give some input for the issue.
Regards,
Umapathy
one more clarification i need i have create some new material for both SFG, FG.
I have run the MRP that time FG only created the planned order other wise 2 nd level and 1 st level SFG not created the planned order.
I have checked and maintain Mrp type : PD, Lot size: EX, Ind / coll indicator : 2 , MRP controller, BOM status all are is correct but Planned order not created?
There might be many reasons why planned orders have not been created for SFGs after MRP run.
Check below parameters
1.Check the stock situation.
2.Check whether any planning file entry exist for both materials in MD21 if not create same.
3.Check whether in MRP4 for dependent requirements not planned setting active for all material?
Check below WIKI for other reasons.
Br
KK