Former Member
Jul 14, 2014 at 08:16 AM

MRP for Co-product

321 Views


Dear Guys

My question is : Material A and B are co-product and material C is their raw material.So I will create BOM like this: 1*A = 1*C + (-1*B).

Then if I create PIR(50 quantities) for material A, the requirement quantity 50 of material C will be calculated by MRP. At the same time,there are the planned receipt quantity 50 of material B. But if I create PIR(50 quantities) for material B, the requirement quantity of material C cannot be calculated by MRP. SAP system will tell us that the material B have no BOM. How to solve it? The resut i expect is the requirement quantity 50 of material C will also be calculated by MRP.

Thanks.

Best Regards.