Hi PS experts

I am facing issue with regards to the report "S_ALR_87013532"

I created projected structure and assigned only one materiel component of total value 15,000 EUR at activity level. Apart from that I have not done cost planning for any other objects in the project.

However when i checked the report "S_ALR_87013532" planned cost is showing as 15,000 at material component level but its showing incorrect figures (21,263) at activity level and its parent level ( Network and WBS element level).

Below are the screen shots of Project structure & the report, please have a look at it & share your expert opinions on the possible reasons for this kind of behavior.

Thanks and Regards,

Naveed

Attachments

reort.jpg (107.0 kB)