How do we transfer Solman organizational unit to ECC system for accounting integration in PPM?

Former Member
0 Kudos

Dear experts,

I am facing a new issue. I am still working on accounting integration.

I have this error message : the cost/revenue rate is not valid in organization.

I don't understand because the organization well appear in PPM, is ok in tcode PPOMA_CRM and cost/revenue rate is defined for this organization in IMG activity.

Did someone already meet this issue ?

Many thanks in advance for your help.

Kind regards,

Cassoké

Accepted Solutions (0)

Answers (2)

Answers (2)

ravi_ekambaram
Active Contributor
0 Kudos

Hi Cassoke,

If your queries are answered, please close the thread by choosing the correct answer. If you have resolved your query on your own, then please share with the community and choose your post as correct answer.

This helps community members to know quickly the answers for the post for which they are searching.

You can refer the below blog on why & how to close the discussions.

http://scn.sap.com/community/support/blog/2013/04/03/how-to-close-a-discussion-and-why

Regards,

Ravi

Vivek_Hegde
Active Contributor
0 Kudos

Hi Cassoké,

This error usually appears if no org unit is maintained in the Project Definition. Did you sync the CRM Org unit in solman with the Org unit of ERP?

Please make sure you have done all activities in following SPRO nodes;

most importantly Replicate Cost/Revenue Rates step. Also check whether these 2 notes are applicable for your ERP system

Note 1308252 - Maintain a revenue element for cost/revenue rate &1

1173077 - Cost/revenue rate X is not valid in organization 00000000

Regards,

Vivek

Former Member
0 Kudos

Hi Vivek,

i read your answer but i have a new question. How can we sync the CRM Org Unit in solman with the Org Unit of ERP ?

Cause im having the same issue as Cassoké.

Thanks for your attention.

Best Regards

António Santos