Dear SAP Experts,
My company is start MRP run in first time, i have created some PIR in Development server and Run the MRP in MD02 Single item / multiple selection.
After that i have delete the Planned order mass in MD16, then i have run the MRP again in plant level.
Many planned order had created due to many old PIR is there in system.
PIR delete only possible the after MRP Run no data found.
So kindly give me the input for mass delete the PIR / Mass change the PIR?
I have also try MD74 , MD75, MD76 but after MRP run many planned order will be created.
So give me the input for delete PIR mass and RE - change the PIR qty what is the t.code to be used?
I am waiting for your reply.
Thanks,
Umapathy
Dear Uma,
Please try reorganisation run for the PIRs, you can use T codes MD74 , MD75 , MD76.
MD74 - deletes only the PIR
MD75 - deletes only the history created against each PIR
MD76 - mass deletion with history
You can also try T. Code: MD62
Hope it helps you.
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Uma,
For reorganization please refer 135807 - Reorganization of planned independent requirements
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.