How to stop DespatchDeliveryNotification_Out XML generation

Hi,

I have a requirement for stopping the generation of DDN XML, when I publish ASN in SNC. This is applicable for some Product of a Vendor only.

For others, I need DDN XML for regular ASN posting in ECC.

Please give your suggestions to help me in finding the best way to do it.

Thanks

Rahul

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Jul 17, 2014 at 01:45 PM

    Hi Rahul,

    You want to stop posting of ASN/inbound delivery creation in ECC based on vendor.

    Then one of the way:You can stop posting of IDoc in ECC by having validation in PI.

    Ask your PI team to have validation check whenever DDN comes with that vendor.

    Regards,

    Nikhil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Nikhil,

      I want to stop the generation of DDn XMl in APO / SNC System itself (not in PI).

      Is there any way to do this ?

      Regards,

      Rahul Sharma

  • Jul 20, 2014 at 02:58 AM

    Hi Rahul

    Is it possible for you to brief the business requirement? Is the requirement that certain vendor /product combinations are stopped from posting an idoc in the system? You wrote "This is applicable for some Product of a Vendor only". You can also explore building a logic in the inbound function module in ECC as you may need a table to maintain a table with vendor/ material/plant combination

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 21, 2014 at 12:13 PM

    Hi Rahul

    Try the below

    BAdI Definition: /SCA/BIF_O_DESDLVRY

    Interface:/SCA/IF_EX_BIF_O_DESDLVRY

    Method: Before Conversion

    Try searching for these solutions in SE18 by Badi Name= /sca/bif*

    😉

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 22, 2014 at 04:28 PM

    Hi Rahul,

    If you want to stop sending ASN xml, then why do you want the supplier to create an ASN. Is there any specific purpose of creating the ASN in SNC?

    If ASN's are for PO's & SA's then would suggest to have appropriate confirmation control set in SNC for the vendor and material combination, there by restricting creation of ASN.

    thanks,

    mahesh.