Hi,

I am trying to close 2013 in asset accounting so that year 2015 can be opened. for this when i try to execute "AJAB" in back ground a screen pops up "Back Ground Print Parameters" i do mention the out put device and print all option after this i check the immediate start check in next popup screen. when i save it a message come up

"Background job was scheduled for program RAJABS00"

But when i go to "OAAQ" closed fiscal year is still "2012" What am i missing here? this print out information is not standard behavior as i haven't seen this in any other back ground processes.

Regards,

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member220526
Active Participant
0 Kudos

After back ground job is being created this is the status i am getting in the spool:

Can any one guide me what options do i have to select before creating the pool request. what are the settings for starting immediately

Former Member
0 Kudos

Hi,

Please check following transaction

AUVA
ASKBN

Depreciation totally posted,

ABST2 - FI-AA reconciliation

former_member220526
Active Participant
0 Kudos

Hi Jeetendra,

The reason why i am not able to open 2015 is because i have to close 2013 first. and the question here is that there was no SAP in my company in 2013 but when i try to open 2015 the system says that i have to close 2013 first as only two fiscal years can be opened at a time. how can i do this? why is system having 2013 open when SAP came to my organization in 2014? please help me.

Former Member
0 Kudos

Hi,

As per my view your year end activity has been pending which you have to carried out ,

please refer my earlier massage ,

there is a last option to change in table directly ( T093C)

MarkusBredel
Advisor
Advisor
0 Kudos

Hi,

this is most likely due to incorrect configuration at production startup.

Which error message does RAJABS bring up when executing in test mode in foreground?

Regards,

Markus

former_member183078
Participant
0 Kudos

Hi ,

first check status of back ground job  whether it is in finished status or waiting. once the job status is finished then you can check OAAQ.

Also i hope you have  you have successfully executed Ajab as well.

Regards

Diwa