Hi,

my newest problem is the next one:

stock saldo is 1000 for a comment

there are 4 planned order requesting this component at the same day with the quantity 300

and moreover a production order some days later requesting still 300.


Availability checks says

1. depreq confirmed 300

2. depreq confirmed 300

3. depreq confirmed 300

4. deprec confirmed 100


ordres confirmed 300 ==> availability -300

The problem of this is the fact tha collective conversion of planned order to production orders converts all those three confirmed planned orders.


Which setting in the scope or anywhere else in the customising would take into account the reservation made in advance?