My customer Need to start the cycle with Creation of equipment and trigger inspection lot automatically contains the number and details of the equipment how can we do this?

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member201357
Participant
0 Kudos

Hi Mostafa Saeed

Didn't try this So not sure amy be i am wrong, you can do autmatic creation of Equipment no. at the time of GR & at the same time system will also create inspection lot but make sure specific inspection point assigned to material master.

Regards

SAP PM

Former Member
0 Kudos

How to create Inspection lot for Equipment without task list & order for the Equipment??

No inspection lot could be generated for order



Message no. IW217

Diagnosis



An inspection type has been defined for the order type in question. An inspection lot should be generated when the order is released. No inspection point field combination has been defined in any of the maintenance task lists used in the order. This is why no insepction lot can be generated.


Procedure


If an inspection lot is to be created, the order must contain at least one procedure which was taken from a maintenance task list and which has been define for one of the inspection point field combinations. This must be done before the order is released.



This is the information message you will get while releasing the order without task list or with task list which is not having inspection point.

Former Member
0 Kudos

So if i cannot do this, can i trigger notification after creating Equipment the generate inspetion lot from this directly ?

peter_atkin
Active Contributor
0 Kudos

Mostafa Saeed

One thing I have never tried is to create an inspection lot without and order or notification. Does anyone know if this is even possible??

You could develop the following process:

  • Equipment->development to create inspection order->at order release an inspection lot is created
  • Equipment->development to create QM notification->create inspection lot

PeteA

Former Member
0 Kudos

I need ,  after creating a new equipment, SAP system will trigger inspection lot to test equipment, including all the tests required

peter_atkin
Active Contributor
0 Kudos

I think you'll need to develop a solution if you want this to happen automatically once the equipment has been created and saved.

PeteA

Former Member
0 Kudos

To Create Inspection Lot, you need the following.

  • Equipment Master
  • MIC
  • Task List
  • Maintenance Order in Released status
  • Once Inspection Lot is created, task list should be assigned to Inspection lot. Task list should be assigned with MIC.

So, its bit complex development to create all the pre-requisites with Inspection lot.

peter_atkin
Active Contributor
0 Kudos

You don't necessarily need an task list/order, you could create the inspection lot from a QM notification.

And if you want to integrate the measurements, then you may need to create measurement points on the equipment.

PeteA

Former Member
0 Kudos

Please provide more information of your requirement.

Inspection lot will contain the calibration activities to be done in equipment. What do you mean by number and details of the equipment?? What you expecting out of that Inspection lot??