Hi All

Route in outbound delivery of ERP is not getting reflected in EWM ODO. I have done below settings in IMG.

Extended Warehouse Management --> Goods Issue Process --> Outbound Delivery --> Route Determination --> Activate or Deactivate Route Determination

DOC TYPE - OUTB

RD/RC Status - 2

RD Sequence - Standard logic

RD ERP - No determination if Route origin is in ERP

Extended Warehouse Management --> Interfaces --> ERP Integration --> Delivery Processing --> Map Routes and Route Schedule from ERP System to EWM

Mapping Route - 2

SCM Basis --> Routing Guide --> General Settings for Route Determination

standard setting

Please help where I missed.

Thanks

Sasidhar Gupta

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jun 25, 2014 at 12:33 PM

    Hi Sasidhar,

    The settings seems fine. Kindly check the following settings also:

    Extended Warehouse Management -> Goods Issue Process -> Outbound Delivery -> Route Determination -> Define Scheduling Within Route Determination

    In here select the relevant doc type and go to node Date/Time Types. If it asks for work area info, enter the EWM client and details. Check if the following two entry exists: TDELIVERY, TOUTYARD.

    Do check under SCM Basis menu if the routing guide is configured.

    Also do give it a try with 'Route determination if Route Origin is in ERP'

    Regards,

    Oritra

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member $@$!DH@R GUPT@

      Hi Sasidhar,

      May I ask you a question? I am trying to configured the TCD function in EWM, I got a very basic question here. Hope you can help on it.

      scenarios is from plant A to customer A via plant B, the plant B is cross-docking plant. I set up two direct route:

      1.   A->B: Plant A to Plant B

      2.   B-CusA: Plant B to Customer A

      And a cross-docking route: A-B-cusA which include above 2 routes. and marked as CD route in EWM.

      my question is when I should do the route determination? do I need to do it in ERP, like have the same route A->B and B->CusA in ERP, and allow it copy to ODO in EWM?  or I should ignore hte ERP route and just do the EWM route determination?

      Can you also list the required configuration for TCD if possible?