cancel
Showing results for 
Search instead for 
Did you mean: 

Production Order not getting cifd across to APO

sb_fernandes
Participant
0 Kudos

When I had cifed the Production Order, it returns the message "sequence-dependent setup activity does not have a mode".

In CIF reconcilation it comes under missing in APO log.

This is not consistent.Some order gets cifd without any issues.Some are having this issue.

Anywhere I m missing.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Roshan,

You are using PDS or PPM to model your production versions in APO? If you use PPM, check if you have only one setup activity and if that activity have the setup checkbox marked.

All the problematic orders have the same material? Did you check if the PDS or PPM was correctly transferred to APO? You have this problem only with production order and not with planned orders?

Are you using sequence-dependant setupo matrix?

Answers (2)

Answers (2)

former_member182332
Participant
0 Kudos

Hi,

Kindly check the below steps:

1) Check if the note 863509 is imeplemented in your system, and very importantly the exit is implemented properly and activated so that it is called during the order transfer

2)In case you have a scenario where a new material is added during production then in that case that material needs to be assigned to an activity, it shouldnt have an dummy acitivity.


BR
Gomathi

former_member182332
Participant
0 Kudos

Hi,

Kindly check if "determine capacity reqrements" is set for the order, Because most of the times this issue occurs due to no generation of capacity requirements.

Hope this helps

BR

Gomathi