Former Member
Jun 19, 2014 at 12:58 PM

Product spec means of transport

25 Views

Hi Team,

We have means of tranport Truck and Rail

Truck - Transport Duration of a Transportation Lane - 48 hours

rail - Transport Duration of a Transportation Lane - 336 hours

I have maintained product spec means of transport in tlane master i.e.Rail - 336hour

But when i checks product view I could see "start date' and "avia/req date" is only showing two days (48h) transit.

Question - After maintaining product spec means of transpor- "rail" why system is taking truck time instend of rail time ?

Please advice me

Rgds

SDB