Skip to Content
0
Former Member
Jun 18, 2014 at 11:48 PM

CHARM Custum status, action - ZMMJ

151 Views

Hi,

i am a big fan of standard Normal change workflow but i need to add custom status to have better control on the changes flowing through.

i am on 7.1 SP6

my landscape is: DEV --> TE --> QA --> PRD

Updated normal change workflow (proposed): To Be Tested --> Successfully Tested --> QA Approved (new) --> CCB Approved (new) --> Imported to Production

I want to leverage the status based import process for both QA and PRD.

So the transport import job for QA via tasklist will run on 'QA approved' status and PRD will run on 'CCB Approved' status.

Once the changes are moved to PRD using the project tasklist, I want the status of Normal change to be set to 'Imported to production'.

please, let me know if anyone has attempted this....and please share the steps to achieve the proposed workflow.

thanks,