Dear all,

Kindly find below image

During confirmation its showing the UOM as Hrs,but i have given in mins in routing.

My requirement is during confirmation it has to come as MIN only,

Kindly please let me know how to process

Regards

Rajasekaran

Accepted Solutions (1)

Accepted Solutions (1)

former_member214153
Active Participant
0 Kudos

Hi Raja,

Can u check in your work center default view and costing view what unit you maintain.

surely you maintain the HR that why its coming in HR. so change it to MIN. and after that create the order and confirm its.

If you want the activity in minute for the current order you have to go in CR02 than operation overview after that double click on the operation--- than standard  tab than change the activity in to minute.

Please let me know if still face the issue

Thanks,

Anurudh

Answers (5)

Answers (5)

former_member1241202
Active Participant
0 Kudos

Dear all,

Thanks,Now its working fine.

After deleting i have changed the work center and then i gave in MINS.

Regards

Rajasekaran

maheshkumar_komatineni
Active Participant
0 Kudos

Hi raja,

please check KL02 Activity types what is the unit of measure maintained for the activities of you work center.

Regards,

Venkat.

former_member1241202
Active Participant
0 Kudos

Dear all,

I have given UOM as MIN only in work center

Regards

Rajasekaran

dejoy
Active Contributor
0 Kudos

Hello,

Make changes here as shown below.CR02>>Costing TAB.

Regards,

former_member184574
Active Contributor
0 Kudos

Hi Raja,

Check in work center in default values tab.. what is the standard value units maintained over there for parameters ????...also check in costing tab what UOM maintained...if possible share the screen shots of work center default values tab, costing tab and routing operations details...

Thanks

Kumar

former_member1241202
Active Participant
0 Kudos
dejoy
Active Contributor
0 Kudos

Hello Rajasekaran,

Please change UoM in work center(CR02>Costing Tab) against activity types.

Regards,