Dear All,

I am facing issue while creating Master Air Schedule. I have selected the option “Gateway” and “Reference” in schedule type configuration. But while creating Master Air Schedule in NWBC, the “Carrier Flight Schedule” field is coming as non-editable.

In "Web dynpro Appl. Screen" field in schedule type config, I am selecting “/SCMTMS/SCHEDULE_AG” (Master Flight Schedule)

Please suggest how to resolve the same and how to assign the Carrier Flight Schedule in Master Air Schedule.

Regards,

Vibhu Gupta

Accepted Solutions (0)

Answers (1)

Answers (1)

NiteshSaluja1
Advisor
Advisor
0 Kudos

Hi,

Kindly check on the item level in Departure Rules rather than Header level.

Hope it helps

Regards

Nitesh

Former Member
0 Kudos

Dear Nitesh,

Thanks for reply.

But when I select schedule at item level departure rule, then system give option to select the days on which carrier schedule is operative. When we select the days using "Shift Key", even then the system select only one single day in our master schedule.

Step 1: I created Master Schedule and selected All Days (Monday to Sunday) in Schedule:

Step 2: I selected Main Leg and select "Assign Schedule". By this below screen opened in which all the days on which carrier schedule is operative appeared. I selected all the days using "Control" Key:

Step 3: By this the system assigned the carrier schedule to my Master Schedule but it selected only one day and unchecked all the other days as below. i have observed that the system select only that day which I have selected first in step 2 and all the days which i have selected using "Control" Key will be marked as unselected in my Master Schedule.

In step 2, if I use "Select All" option instead of selecting days manually, then carrier schedule will not at all assigned to my master schedule.

Kindly help in this regards.