PM - PP Integration

Former Member
0 Kudos

Guru,

Kindly outline the requirements(step by Step)  for PM - PP integration. i know there is a link during capacity planning, but i want to know all the details and requirements

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Capacity Planning:

  • Assign the Production Work Center in Equipment Location tab
  • Assign System Condition (In Use / Not in Use) in PM Order creation
  • Create Production Order with work center assigned to PM order Equipment
  • Do the Capacity Evaluation. System will propose that Work Center is not available for production if PM Order dates & Production order dates overlap
  • But this can be overruled as its just proposal from the system.

Performance Based Maintenance Plan:

Based on Quantity Produced / Run hours of Equipment, Maintenance order can be created.

  • Create Measuring Point with UoM as HR / with EA
  • Create Equipment as PRT with PRT view
  • Create Maintenance Plan with cycle as HR or EA
  • Assign Measuring Point & Maintenance Plan in Equipment PRT view
  • Assign this PRT in Production routing
  • Assign Usage value formula appropriately for RunHours or Qty
  • Create Production Order
  • Do the Qty confirmation for Production Order
  • Based on the Usage value assigned in routing, Measurement document will be created for RunHours / Qty automatically for the Measuring point assigned in PRT Equipment master
  • Plan the Scheduling IP30 so that based on Measurement document value & Cycle frequency in Maintenance plan, Maintenance order can be created.

There are many threads with these PP - PM Integration. Please do some more search.