Hi experts,

we are using the order-net in SAP.
This means that you have the complete structure of a part already defined with the orders.

If you finished a sub-order it will be booked automatically into the higher-level order.

So if you have the following structure

A

--B

C

--D

--E

--F

if you finish Order E it will be booked automatically into Order C.

For this booking we get an material document which includes a 101 and 261 movement type in one.

As we are facing troubles with our serialnumber-generation, I want to get two material documents.

The first one which makes the 101 movement type and gets the part on stock and the second which makes the 261.

Does anyone know, if this is possible to get two material documents instead of one?