Hello Friends,

In my current business process STO is created to move goods to virtual storage location.

Goods are transferred to project stock ( 412 Q).Outbound delivery for STO-->Picking request--> Inbound delivery--> Transfer to stock in transit ( 641Q).Now movement type 101 Q will be used for STO to create GR for plant without any accounting doc.Goods are issued for consumption and charged under the project ( 221).

Now my question is a) how can I issue material to PM work order from project stock ( 412 Q) using above process if possible.?

b) How can I consume stock for PM work order from project stock without moving this to virtual storage location ( if I want to cut down the virtual storage location step and manage directly between project stock and work order).

Thank You!