'WAIT' step not working...

Hi Experts,

I have two programs, one for PO event - created and the other for event - changed.

I have given BUS2012 - created in 'start events' tab of my WF. Now, i have a 'wait' step, that waits untill a PO is changed.

Where should i bind this event in my workflow, such that the workflow continues after i execute my second program, which creates an event - 'changed'??

Regards,

Viswa .S

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on Jun 11, 2014 at 09:45 AM

    Hi Srinivasan,

    As far i know, moment you mention event in wait for event step, entry will be created in system and can be hecked from t-code SWE3. if no entry has been created for your event please create one and let know if it works?

    Regards

    Ajit

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 11, 2014 at 07:03 AM

    Check the different step types in the workflow builder. There is a step type "Wait" (or was it "Wait for event"). Just set that kind of step into your workflow and define your event there.

    Kind regards,

    Karri

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 11, 2014 at 09:14 AM

    Hi Viswa,

    I think your requirement is :

    1.) Trigger 1st workflow when PO get created. This is DONE

    2.) If a PO get changed then trigger Changed event based on your custom program and 2nd workflow will get triggered and 1st workflow will completed. This is not DONE.

    Please let us know how you have tested your wait event is not working ?

    To achieve the same you have design your workflow with parallel processing using FORK in 1st workflow. One branch of FORK will contain actula approval process and other branch will contain wait step. You donot have to do any binding just assign the business object and event and click on auto binding.

    Please let us know if you need more detail.

    BR,

    Prakash

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Prakash,

      I have only a single WF. My requirement is to trigger the WF for the 'CREATED' event, then it has to wait untill the 'CHANGED' event.

      Should i bind BUS2012-CHANGED anywhere else (like in header data) other than the step type "WAIT"?

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.